Kakrapar Atomic Power project (KAPP3)
29 Sep 2023 3 mins Download PDF
Kakrapar Atomic Power project (KAPP3)
- It is the largest indigenously developed 700-megawatt electric (MWe) nuclear power reactor unit in Gujarat attained it first criticality in 2020, has started operations in 2023.
- First criticality signifies the initiation of a controlled, but sustained nuclear fission reaction in the nuclear power plant.
- It is a variant of the Pressurised Heavy Water Reactor (PHWR) which uses natural uranium as fuel and heavy water as the moderator.
- The power plant also addresses the excess thermal margins
- Thermal margins refer to the extent to which the operating temperature of the reactor is below its maximum operating temperature.